|
The
Idiots' Guide to Highways Maintenance
Copyright
© 2000/08, C.J.Summers |
20MM. HOT ROLLED ASPHALT PRECOATS -
SPREAD RATES
All these chippings have been placed by hand
in laboratory conditions for the specific purpose of demonstrating what differing
rates of spread look like in perfect conditions.
NOTE - The spread rates, in kgs. per square metre,
for 14mm. precoated chippings will be lower.
With smaller nominal size chippings you obtain the appropriate surface cover
with less mass of chippings than you do with a larger size chipping.
You will see evidence of this fact if you look at the rates of spread of the
various sizes of chipping for surface dressing.
It is an easy enough procedure to determine rates of spread of chippings per
square metre for any source of chipping, you only need a measured square metre
and an accurate balance.
Rates of spread of chipping will vary slightly according to the density of the
aggregate, and the nominal size of the chipping within the permitted size range,
e.g. within the 14mm. to 20mm. size range for 20mm. precoats.
This is why you get the terms "bold" or "small" applied to a
particular nominal size chipping, i.e. are the bulk of the chippings nearer a
20mm. size or a 14mm. size.
BUT, do not forget, it is the TEXTURE DEPTH of the surface that is critical, it
is possible to spread the correct amount of precoats and then roll all of them
in to the mat leaving little if any surface texture.
This is why the nature of specifying was changed from a required rate of spread
of precoats to a texture depth requirement.
A surface texture of 1.5mm., by "sandpatch" is the usual
criteria for trunk roads and motorways whether it is Thin Surfacing or HRA and
precoats, although this has recently decreased to 1.2mm. for low speed roads.
For current guidance on texture depth requirements relevant to different
surfacing materials and highway locations see,
Interim Advice Note (IAN) 101/07 - Clause 921 -
Table 9/2
The recommendations here, for motorways and trunk road are often deferred to for
local authority work, at least on the major roads within that network.
If the above table of texture depth requirements, or some similar specific
requirement is not inserted into the contract document, then the default
requirement will be that contained in,
BS 594987 - Asphalts for roads and other paved areas -
Specification for the transport, laying and compaction and type testing
protocols
The actual specification of texture depth is stated to be "site
specific and outside the scope of this standard", however
typical examples of texture depth requirements are included, for guidance, as a "Note",
see Chapters 7 & 8 for further information.
It is worth pointing out that there is in BS 594987
a large amount of excellent guidance contained in the many "Notes"
included throughout the document. These "Notes"
cannot be used as part of the specifying text, but will assist in the inclusion of
appropriate specifying paragraphs in you contract/works document, should you
think it necessary.
 |
|
 |
|
 |
|
 |
|
 |
A
45mm. layer of hot rolled asphalt wearing course is laid with a paver and
then the appropriate rate of precoats is applied to the asphalt surface,
with a chipping spreader, to achieve the required texture depth.
It is most important to realise the precoats are held in the asphalt
because the bitumen coating has been melted by the heat of the laid
asphalt and the chippings are then positively bonded to the surface, also being
partially compacted into the surface. |
The
two most common causes for chipping loss from the the surface of the hot
rolled asphalt are :-
- Chilling of the surface of the laid
asphalt mat while waiting to receive the application of precoated chippings, so
that there is insufficient heat in the surface of the asphalt to melt
the layer of bitumen coating the chipping, that should provide that
"glueing" bond of chipping to asphalt.
- Overheating the chippings and bitumen
at the time of precoating so that the bitumen binder is
"burnt" and rendered inert, this can happen even after the
coating process has taken place, i.e. when/if the hot precoated
chippings are stockpiled in deep stockpiles rather than spread into relatively
thin layers to assist cooling.
"Burning" / "coking" / "carbonising" of
the bitumen coating around the chipping means that there is no "active" binder to melt and bond
the chipping to the asphalt.
The two most common causes for chipping
loss into the laid asphalt mat are :-
- The laid asphalt is too hot, i.e.
above permitted rolling temperatures (and is likely to have been mixed
too hot so that the asphalt has already been "damaged" and
will have a reduced life) and the chippings will be pushed completely
into the asphalt, and will not provide any texture.
- The supplied asphalt contains moisture
in the sand element of the mixture due to insufficient drying of the
sand. This makes the asphalt unstable, and can even make it impossible
to lay to correct level through the paver because of this instable
nature. The applied chippings are quickly lost into the asphalt layer
when rolling takes place. This phenomena often takes place after
periods of overnight heavy rain when the sand stockpiles at the quarry
/ production plant are not under
cover, and the speed of aggregate/sand drying has not been altered to
take account of the increased moisture.
|
 |
Information is to be found here
describing, The
process of laying hot rolled asphalt and precoats.
[ Top of Page ]