| [ Top ] | Fast Photographs Page |
|
The Idiots' Guide to Highways
Maintenance |
RAISING IRONWORK FOR BITUMINOUS OVERLAYS
CONTENTS
Method of raising street
ironwork when overlaying with bituminous material
Specifications
relating to street ironwork
General notes to
lifting ironwork
Personal Note
METHOD OF RAISING STREET IRONWORK WHEN OVERLAYING WITH BITUMINOUS MATERIAL
![]() |
Note
the considerable depth of excavation that is necessary to
"lift" a large manhole. The surrounding road pavement has been cut back to a sound vertical joint. The manhole casting is raised on thin engineering bricks or special "tiles" for finer adjustment. The bricks and tiles must be of engineering quality. It is usual these days to use "fast set" cementitious compounds as the mortar, and setting times can be as little as 15/20 minutes, and this allows raising the ironwork on the day of the bituminous surfacing. Although "normal" mortar is quite acceptable in new construction, or where there is a road closure of sufficient duration to allow the mortar to reach full strength. |
![]() |
In this example the casting is being raised by thin engineering bricks on only one side to allow for the camber of the road, the remainder of chamber top is just receiving a bedding layer of mortar. |
![]() |
The
whole manhole cover is now successfully raised to its new
height. It is now required for the all loose material to be removed from the excavation and for bituminous material to be hand placed around the ironwork in successive layers and fully compacted to prevent any later settlement of the surrounding bituminous material due to compaction by traffic. The above most important operation is often overlooked and is a contributory factor to early failure of ironwork. |
![]() |
In
this photograph you are able to see the layer of thin
engineering bricks that have raised the manhole cover the
required amount for the thickness of the bituminous
overlay. Fast set compound will now be grouted all around the manhole casing to secure it firmly. Once the mortar has hardened and at the time of paving all loose material must be removed and suitable bituminous material hand placed and compacted prior to the actual surfacing. |
![]() |
A
cluster of stop-valve covers that have been raised. The excavation will be sucked clean with the road sweeper attachment. When all loose material has been removed bituminous material will be hand laid around the boxes and compacted with a hand rammer to existing surface level, prior to the paver laid bituminous mat being applied. The correct placing of bituminous material around raised ironwork and its full compaction is an extremely important part of the ironwork raising procedure. |
SPECIFICATIONS
RELATING TO STREET IRONWORK
BS 497 : Specification for manhole covers, road gully gratings
& frames for drainage purposes :
Part 1 : Cast iron and cast steel
N.B. THIS SPECIFICATION WAS WITHDRAWN WITH EFFECT FROM 30th JUNE
1995,
and is superseded by,
BS
EN 124:1994:Gully tops and manhole tops for vehicular and
pedestrian areas : Design requirements, type testing, marking,
quality control
The
specification includes such criteria as loading, design and
dimensions.
BS EN 124:1994 was so difficult to understand BS 7903 was introduced to
help make things a little less confusing.
BS 7903:1997:Selection and use of gully tops and manhole covers
for installation within the highway
Highways Agency Guidance Document - HA
104/2 - Chamber Tops and Gully Tops for Road Drainage Services
GENERAL NOTES TO
LIFTING IRONWORK
The term ironwork used in relation to highways maintenance and
construction means gulleys (drains), manholes, stop-tap covers,
inspection chamber covers, etc. etc..
All these products will be manufactured to the appropriate
British Standard with regards to approved designs, dimensions and
strength.
The actual specification and testing of ironwork items is a
separate issue to the setting or lifting of such products, but
without the correct setting of manholes covers and gully gratings
they will be subject to unnecessary high levels of loading that
may be above their design criteria and therefore will be the
cause of early failure.
To achieve maximum effectiveness and strength ironwork must be
lifted / installed / bedded in the correct way, poor workmanship
in installation is a big cause of ironwork failure.
Ironwork that has been lifted poorly will "move" and
settle, making the road unsafe, and cause premature failure of
the pavement construction / surfacing / overlay.
Obtain a copy of the scheme design or overseeing organisation
specification for full details of how the particular piece of
ironwork should be lifted.
However, the basic requirements amount to good practice, the
chamber shall be soundly constructed and pointed (if brickwork),
some chambers / gulley pots are pre-made in concrete.
The gully pots that are preformed in plastic MUST be completely
surrounded with fresh concrete, according to the specification,
if the gully is to achieve the correct load carrying strength.
Failure to achieve this total surround of appropriate, fresh, concrete is often
a cause of the settlement of ironwork.
Ironwork in general shall be bedded on an approved mortar, quite
often a rapid setting mortar,
e.g. a strength of 10n./mm. squared at 2 hours.
At the time of lifting it is not always known what will be
required to successfully raise the ironwork to the new level, so
a broad selection of materials and items should be carried by the
lifting gang, e.g. fast set mortar, engineering bricks,
engineering quality "tiles", steel strips to support
ironwork, etc..
The frame of whatever item of ironwork you are lifting must be
completely supported by the method of lifting/setting you have
adopted.
Ironwork can be lifted before or after the wearing course has
been laid, but it is usually preferred to lift before final
surfacing if possible as this allows more thorough inspection of
the ironwork lifting, and it avoids extra joints in the surfacing
material and allows better compaction of the bituminous surface
course.
It is usually a requirement of the specification, e.g.'s
BS 4987:Part 2 and BS
594:Part 2, ( BS EN 13108 : Parts 1 & 4 and BS 594987 from the 1st.of
January 2008)
that vertical faces of manhole covers and gulleys are cleaned and
painted with a thin uniform coating of 50 or 70 penetration grade hot bitumen or
cold applied thixotropic bitumen compound of similar grade before coated
macadam/hot rolled asphalt is laid.
Safety of operatives and the public shall be paramount at all
times, during the lifting of ironwork, and suitable signing and guarding must be
in place while the work takes place.
The ironwork may
be in a lifted condition for a while before surfacing takes place and while traffic is
allowed to use the highway.
Appropriate signing and guarding must be in place to inform the driving public
of any hazard.
I
try to refer to as few commercial sites as possible in compiling
my site, but when a site offers useful or interesting information
about a subject I make an exception.
Useful
information on the manufacture and specification of inspection
covers and gratings can be found by pressing,
---------------------->
HERE
Useful
information, and illustrations, on gully pot chambers and associated pipes and
pipework can be found by pressing, ------ >
HERE
Personal
Note
It
is sad to state that in my experience when I have been asked to
investigate the failure of road ironwork, which usually means
nothing more than the lifting of the grating and sticking your
head down the chamber to have a good look, it has been the
standard of workmanship that has been to blame for the failure.
This lack of workmanship seems especially prevalent when road
gullys are raised to allow for an overlay of bituminous
surfacing.
In this situation it is often the case that the ironwork is
raised correctly to the right level, i.e. the surface level of
the finished wearing course, but with a minimum of effort.
When you look at the standard of "lifting" it leaves a
lot to be desired in terms of correctly placed and mortared in
brick work and quarry tiles ( quarry tiles are used for small
lifts ) to form a strong load transferring bed for the gully.
The finished bituminous surfacing will look fine for a while, but
then you will see the tell tale cracking start to appear around
the gully showing that the supporting brickwork between the gully pot/chamber
and gully was not correctly
constructed when raised.
And, I will repeat once more it is most important for all loose material to be
removed from around the lifted ironwork and suitable bituminous material to be
hand placed and fully compacted before the main paver laid surfacing is
performed.
Do you know I have even seen loose material, on the old road surface, in front
of the paver, removed by sweeping it in to the cavity around the lifted
ironwork, and then "suits" wonder why early ironwork failure occurs,
and if there is no "supervision"
on site it is likely to
keep happening.
Correct procedures in placing hot-mix bituminous materials around lifted
ironwork adds considerably to the strength of the ironwork.
Again
as I have said many times in the pages of this website there is
no substitute for good site supervision to ensure work is
correctly carried out, "paper" saving on good supervision is not a
saving at all.
Contractors who perform the work correctly, and there are some
excellent, conscientious gangs who specialise in this type of
work have nothing to
fear, in fact they will benefit because contractors with poor
working practice when gully lifting will be exposed by good site
supervision and should be removed from the tender list.
If the overseeing organisations do not penalise contractors /suppliers who
perform badly and do not support contractors/suppliers who provide a good
service, the quality of all products and service supplied to maintain highway
networks will follow a downward spiral.
I will also make a separate and strong point that when "plastic
former" gulley pots are used, they are meant to be surrounded by a
substantial amount of good quality concrete. If you do not follow, and enforce
good engineering practice you will have gulley failures that are nothing to do
with how well you actually set the ironwork.
Do not tell me bad practice does not happen, it does, you need strong on site
supervision, if you do not penalise the contractors that do it badly you are not
supporting the contractors who do it correctly.
[
Top of Page ]