| [ Top ] | Contents Page |
The Idiots' Guide to
Highways Maintenance |
DRAINAGE (CONTROL
OF WATER) IN ROAD PAVEMENT CONSTRUCTION AND MAINTENANCE
CONTENTS
INTRODUCTION
SUBGRADE DRAINAGE
EARTHWORKS CONSOLIDATION
FROST HEAVE
SUB-BASE DRAINAGE
WATER DAMAGE TO A ROAD
PAVEMENT (FAILURE DUE TO HYDRAULIC PRESSURE)
WATER DAMAGE TO A ROAD
PAVEMENT (FAILURE DUE TO BINDER STRIPPING)
ROAD PAVEMENT STRUCTURAL
FAILURE
DTP DESIGN MANUAL HD 25/94
DRAINAGE 0F POROUS SURFACE
COURSES
WATER TABLE LEVEL
INTRODUCTION
DRAINAGE is VERY! VERY! VERY!
IMPORTANT, both in relation to road pavement construction and
maintenance.
You MUST keep the water-table low to prevent the moisture content
of the subgrade increasing, and hence decreasing the subgrade
strength, measured by the CBR value, on which the road pavement
was designed.
If this is not done by the use of french drains, or even open
ditches adjacent to the highway, the road pavement will weaken
and fail.
The water-table of naturally occurring ground will rise and fall
from winter to summer, bear this in mind when designing the road,
and design for the highest water table (weakest subgrade)
conditions.
Good drainage will help to keep the water table (and strength) of the road
pavement in equilibrium.
Also the road pavement itself must be constructed so that it will
drain in the event of a failure of the integrity of the surfacing
layers, i.e. if water is able to enter the road pavement there
must be a path for it to exit.
The internal drainage function of a road pavement is usually
performed by the GSB layer, this itself MUST be drained in some
way.
In my younger days this function was provided by a french drain
on the lower side channel and periodically piped to an outside
drain or open ditch, but this practice seems to have become
redundant.
Water below the road pavement must be kept low and not be allowed
to rise up into the construction layers, (and water CAN flow
upwards, by capillary action).
IF WATER IS
ABLE TO ENTER THE ROAD PAVEMENT, FOR WHAT EVER REASON, THE DESIGN
OF THE ROAD PAVEMENT SHOULD BE SUCH THAT THE WATER HAS A WAY OUT,
THIS IS USUALLY THROUGH A SUB-BASE LAYER THAT IS DRAINED TO AN
INSTALLED DRAINAGE SYSTEM.
IF WATER CANNOT FIND A PATH OUT OUT THE ROAD PAVEMENT FAILURE OF
THE HIGHWAY WILL BE PREMATURE AND SWIFT.
![]() |
![]() |
| BUT, IT IS A
MUCH BETTER POLICY, WITH APPROPRIATE HIGHWAY MAINTENANCE
PROCEDURES, TO PREVENT WATER ENTERING THE ROAD PAVEMENT. DO NOT LET SITUATIONS SHOWN ABOVE EXIST FOR LONG PERIODS OR SERIOUS FAILURE WILL RESULT. |
SUBGRADE DRAINAGE
The subgrade is the layer of
naturally occurring material the road is built upon, OR It can
refer to the imported fill material that has been used to create
an embankment upon which the road pavement is constructed.
The strength of the subgrade or the material constituting the
subgrade is commonly measured using the CBR test.
The strength of the subgrade is an important factor influencing
the thickness of the road pavement design.
Where the subgrade is weak, i.e. a low CBR, this will usually be associated with
clay subgrades and/or soils that have a high clay content, it will be necessary
to have a capping layer over the subgrade to increase the
strength before the actual road pavement thickness is designed.
The strength of the subgrade can be maintained or even increased
by good drainage, and bad drainage may weaken an existing good subgrade.
EARTHWORKS CONSOLIDATION
Consolidation is the
compression of soil under steady pressure due to the expulsion of
water from the voids.
So, you MUST remember soil can consolidate after it has been
fully compacted, especially if the soil has a high moisture
content.
Consolidation may take many years depending on the drainage
conditions of the embankment / subgrade / foundation.
If the load is removed from the soil, water may return to the
voids causing swelling, and heave of any road built in this
situation.
FROST HEAVE
The term frost heave is
referring to the phenomena where a road will actually
"heave", i.e. rise up above its normal level due to the
action of frost.
It is uncommon in this country because of the relative mildness
of the winters, and the good engineering practice that has been
taking place for many years, i.e. our design standards have
specified that no frost susceptible material is included in the
top 450mm. of any road pavement, also good drainage to prevent
water availability.
Where frost heave does take place the process is such that the
freezing takes place from the surface downwards,
"sucking" water up from lower levels, laying down
subsequent layers of ice causing the road to expand upwards,
i.e."heave".
For frost heave to take place you need road construction material
that absorbs water and water for it to absorb, so good drainage
helps prevent frost heave.
SUB-BASE DRAINAGE
The sub-base also acts as a
drainage layer,
BUT IT CAN ONLY DO SO IF YOU INCORPORATE A DRAINAGE SYSTEM
(HOWEVER BASIC) TO REMOVE THE WATER FROM THE SUB-BASE.
Sub-base is also a load spreading layer, especially during
construction, carrying site traffic and protecting the subgrade,
to an extent, (as long as conditions are not too wet).
WATER DAMAGE TO A ROAD
PAVEMENT (FAILURE DUE TO HYDRAULIC PRESSURE)
Once water has entered a road
pavement, water damage is initially caused by hydraulic pressure,
i.e. vehicles passing over the road pavement impart considerable
sudden pressure on the water present in the road pavement, this
pressure forces the water further into the road fabric and breaks
it up, this process can be very rapid once it begins.
Water that has entered the road pavement and is subject to the
process of freezing (expansion) and thawing during the winter
also brings about the swift failure of the road pavement.
Eventually the water will descend to the subgrade layer below the
road pavement and weaken this layer thus lowering the CBR of the
subgrade which the road pavement design was based upon, and deep
seated failure of the road will begin.
WATER DAMAGE TO A ROAD
PAVEMENT (FAILURE DUE TO BINDER STRIPPING)
Most aggregates have a greater
affinity for water than they do bitumen, and with the presence of
water and movement of the aggregate it is quite possible for the
binder film on the aggregate particle to be broken and water to
come in to contact with the aggregate surface.
Once the integrity of the binder layer has been broken it will
depend upon the chemical nature of the aggregate particle and the
viscosity of the binder as to how long it will be before
stripping of the aggregate particles becomes an engineering
problem.
Depending on the viscosity of the binder and the thickness of
the binder film surrounding the aggregate the stripping of the
bitumen will occur hardly at all, fairly slowly or quite quite
quickly.
This can be compared to
a film of highly viscous 50pen. grade bitumen enhanced with
cellulose or mineral fibres which will create a thick stable
coating of bitumen around the aggregate particle,
to
a low viscosity, highly workable, low temperature, hand-lay
cutback material for emergency patching or very low stress sites.
The first example will
be highly resistant to stripping and is the binder coating used
on most stone mastic asphalts, and other Thin Surfacing surface
courses (wearing courses), many of these surfacing materials
actually designed to allow the passage of water through the
material matrix.
However, because of their exposed position in the road pavement
structure even these binder systems can break down over time, (and the access of
oxygen to the internal matrix of the materials will increase the rate of
oxidation of the bitumen).
The second example
strips quite readily, and in most cases should only be regarded
as a temporary measure before being removed and a more stable
bituminous material used to replace it.
There are many degrees
of stripping between the two examples I quote, and it is a fact
that some aggregate sources are more prone to stripping than
others.
But, I do not want to cause panic amongst those less familiar
with bituminous mixtures, it is unlikely that you will have
significant stripping with any material that has a 200pen. grade
bitumen or above (meaning stiffer i.e. 100pen., 70pen., 50pen.), with a sensible bitumen content, combined with
a reasonably proportioned, dense, aggregate grading.
Most of the dense
roadbases and basecourse, and close graded wearing courses in BS 4987 (BS EN
13108:Part1 from 01-01-08), coupled with the appropriated grade of binder will give you
these properties.
Hot rolled asphalts found specified in BS 594 (BS EN 13108:Part
4 from 01-01-08) in general have
higher binder contents of stiffer grade bitumens and as such are
very unlikely to incur binder stripping.
ROAD PAVEMENT STRUCTURAL
FAILURE
This is when the
pavement has failed, maybe not completely, but in a major way.
The pavement is no longer able to absorb and transmit the wheel loading through the fabric of the road without causing fairly rapid further deterioration of the road pavement.
The layers making up the road
pavement have failed for various reasons, but one of the most
common is poor drainage, either by :-
Lack of adequate drainage provision in the original road pavement
design,
Lack of maintenance of the drainage so that it no longer
functions in a correct manner and the water table has risen thus
weakening the road pavement,
Failure of the impervious nature of the surface course (wearing
course), or the binder course (basecourse) where the surface
course is a porous textured material, thus allowing the passage
of surface water in to the road pavement matrix.
DTP DESIGN MANUAL HD
25/94 - ROAD FOUNDATIONS - CBR - CAPPING - DRAINAGE
This standard forms part of the :-
DESIGN
MANUAL FOR ROADS AND BRIDGES : VOLUME 7 - PAVEMENT DESIGN AND
MAINTENANCE : SECTION 2 - PAVEMENT DESIGN AND CONSTRUCTION : PART
2 - HD 25/94 - FOUNDATIONS
It is a very useful standard, describing the requirements for a
road foundation, the ways of testing for subgrade strength, the
strengths needed, and the ways of creating a stronger subgrade
prior to road pavement construction.
It includes useful tables on subgrade CBR's and required capping
layers, along with the drainage requirements relating to
foundations.
DRAINAGE 0F POROUS
SURFACE COURSES
It has to be understood
that in some circumstances surface course (wearing course)
materials are deliberately designed to be porous so that
"spray" from vehicle wheels will be substantially
reduced, improving visibility in wet conditions.
The porosity of the interconnecting voids of the surface course
matrix can be verified by a "porosity test".
This test is a measure
of the porosity of Porous Asphalt or other open textured
bituminous mixture, i.e. how quickly the water will drain through
it, and the test is usually performed shortly after laying to
check that the material/surface complies with the specification.
The method of the test is to be found in BS DD 229 : 1996.
It will also be performed from time to time to to test that the
interconnecting voids which allow drainage have not become
clogged.
The test is described in,
Clause 938:Porous Asphalt Surface Course, of Volume 1, of the
Specification for Highway Works.
There is an average minimum
requirement of 0.12s(-1).
WATER TABLE LEVEL
You MUST keep the water-table low to prevent the moisture content
of the SUB-GRADE increasing, and hence decreasing the CBR value
on which the road pavement was designed.
If this is not done by the use of french drains, or even open
ditches the road will weaken and fail.
The water-table of naturally occurring ground will rise and fall
from winter to summer, bear this in mind when designing the road,
and design for the highest water table conditions.
Water below the road pavement must be kept low and not be allowed
to rise up into the constuction layers, (and water CAN flow
upwards, by capillary action).
The fact that road drainage needs periodic maintenance just like
an other part of the road network must not be ignored, and it is
a lot less expensive than reconstructing failed road pavement.
Water that enters the road pavement from the surface MUST have a
drainage path out.